Description
JML Engineering worked with The Sharp Group to provide Construction Engineering Services during the Construction of the Wiggle Creek Culverts on Highway 599 north of Silver Dollar, Ontario. The replacement culverts were precast concrete.
JML Engineering completed designs for the Temporary Modular Bridge, Temporary Flow Passage System, Culvert Erection Procedures and Inspection of the installed culverts for conformance with Contract Documents.
The design work included using the geotechnical data provided in the Contract Documents to design the foundations for the Temporary Modular Bridge and to design the crane pads for the installation of the culverts.
A site visit was completed for an inspection of the Temporary Modular Bridge and a Certificate of Conformance was provided.
During the erection of the concrete culvert elements full time inspection was completed to immediately respond to any issues during erection and certify the placement of each culvert element. Upon completion of all of the precast culvert elements a Certificate of Conformance was issued.